General Assumptions

Id Activity Value Uom Description Remarks Source
21 Reinstalling ○ ○ Time needed to restore other mechanical connections: see dedicated table expert judgment
22 Leak test 0.50 h Time needed to connect the high pressure nitrogen generator expert judgment
23 Leak test 1.10 ○ Leak test pressure to operating pressure ratio expert judgment
24 Leak test 1,400.00 Sm3/h High pressure nitrogen flow rate TO BE DEFINED BASED ON PROJECT PROJECT SOURCE
25 Leak test 0.25 h/conn. Time needed to check each flange for leaks after the test pressure is achieved expert judgment
26 Air Removal 0.50 h Time needed to connect the nitrogen generator expert judgment
27 Air Removal 0.21 ○ Initial oxygen concentration (in case leak test has not been performed) expert judgment
28 Air Removal 0.03 ○ Target oxygen concentration expert judgment
29 Air Removal 2.00 ○ Pressurization pressure (applicable to purging by pressurization/depr. cycles) Assumed equal to Purging expert judgment
30 Air Removal 1.00 ○ Discharge pressure (applicable to purging by pressurization/depr. cycles) Assumed equal to Purging expert judgment
31 Air Removal 1,400.00 ○ Nitrogen generator flow rate Assumed equal to Purging expert judgment 342101BPST02508 34210ABPRV02054
32 Commissioning & Start up 1.00 h Temperature restoring time expert judgment
33 Commissioning & Start up 0.50 h Pressure restoring time Assumed equal to Depressurization time expert judgment
34 Commissioning & Start up ○ ○ Level restoring time Assumed equal to Draining time expert judgment
35 ○ 2.00 ○ Maximum numbers of crews working in parallel for isolation/blinding expert judgment
36 ○ 0.80 ○ Efficiency of maintenance crew Not applied to essentially labor-free activities (i.e. Cool down and Ventilation) expert judgment
37 Item conveyance to workshop 1.00 h Loading / Unloading expert judgment
38 Item conveyance to workshop 1.00 h Travel to WS expert judgment